The City continues to invest in 32 Avenue to improve traffic flow, increase road safety and support growth.

Project description

32 Avenue is a key east-west link serving South Surrey including Rosemary Heights, Morgan Creek, and North Grandview Heights neighbourhoods. It also serves the Campbell Heights Business Park and is a designated truck route.

We have already widened 32 Avenue from King George to 168 Street to improve traffic flow, increase road safety, and support city growth. Next, we plan to widen 176 Street to 196 Street in multiple phases to improve road safety for cyclists and pedestrians and ensure traffic keeps moving to support access to jobs and efficient movement of goods and services to Campbell Heights. 

Campbell Heights plays a crucial role in Surrey’s economic development by fostering businesses and industries. The Campbell Heights Business Park is one of Surrey's largest industrial and commercial hubs creating over 7000 jobs for the region.


Project timing

Improvements will be made in phases:

Phase 1: 184 Street to 188 Street

Construction to start in spring 2024 and be completed in spring 2025.
Work will also include installation of BC Hydro’s planned duct bank to service the Campbell Heights area.

Phase 2: 176 Street to 184 Street

Construction to start in spring 2025 and be completed in 2026.
Work will also include upgrades to drainage infrastructure to improve drainage conveyance to Erickson Creek and support future upland development. 

Phase 3: 192 Street to 196 Street

Construction to start in 2027 and be completed in 2028.

 

Key road improvements

  • Repaving and widening the road from two to four travel lanes to improve traffic flow now and into the future
  • Installing a new traffic signal and pedestrian crossing at 32 Avenue and 188 Street to improve access and road safety
  • Adding a multiuse path on the south side of the street to make it safer to cycle and walk

     

Map of improvements

View as PDF

Map of improvements from 176 St to 184 St
Map of improvements from 184 St to 188 St

 

Project design

Below are typical cross-sections for improvements between 176 Street and 184 Street.

view as PDF

 

Road view of alignment

 

 

Contact

If you have questions or comments, please contact the Project Delivery Division at 604-591-4253 or engineering@surrey.ca