Status

Awarded


Jacob Bros. Construction Ltd.
$4,044,482.39

Closing Date

February 02, 2016 - 3:00 p.m. (local time)


Revised March 24, 2020

Contact

Name of Owner's Representative:

Goran Corda, BTech, Project Manager
City of Surrey - Engineering Department
13450 - 104 Avenue
Surrey, BC  V3T 1V8

Tel:  (604) 598-5853
Email:  GCorda@surrey.ca

The Owner invites tenders for:
Widening of King George Boulevard from two to four lanes complete with bicycle, pedestrian, and public transit facilities. The Work includes, but is not limited to, road reconstruction, pavement patching, milling, curb and gutter, concrete sidewalk, storm drainage installation, manhole adjustments, lawnbasins, catchbasins, paving and related work, landscaped boulevards, erosion and sediment control, and traffic control.

Contract Documents are available at:
This tender is being issued electronically through the BC Bid website (www.bcbid.gov.bc.ca) where any interested party may download the tender documents directly from the BC Bid website.  No registration, tracking or other recording of tender document holders will be performed by the Owner. All addenda or further information will be published through the BC Bid website.  It is the sole responsibility of the tenderer to monitor the BC Bid website regularly to check for updates.

Addendum No. 1
(See BC Bid Website - (www.bcbid.gov.bc.ca)
Issue Date:  January 22, 2016

Addendum No. 2
(See BC Bid Website - (www.bcbid.gov.bc.ca)
Issue Date:  January 26, 2016

Addendum No. 3
(See BC Bid Website - (www.bcbid.gov.bc.ca)
Issue Date:  January 27, 2016

The Contract is based on the MMCD Platinum Edition.

Tenders are scheduled to close:
Tender Closing Time:  3:00pm, local time
Tender Closing Date:  February 02, 2016

Tenders should be submitted in a sealed package, marked on the outside with “Tenders for King George Boulevard Widening From 32 Avenue Diversion to 152 Street” and must be received at the first floor Main Reception / Information Desk, Surrey City Hall, 13450 – 104 Avenue, Surrey, BC Canada V3T 1V8.

Company Amount Awarded to:
Jacob Bros. Construction Ltd. $4,044,482.39 Jacob Bros. Construction Ltd.
B&B Contracting (2012) Ltd. $4,086,600.00  
Mainland Civil Site Services Inc. $4,266,935.00  
BD Hall Constructors Corp. $4,408,623.00  
Tybo Contracting Ltd. $4,488,750.00  
Eurovia British Columbia Inc. $4,606,467.00  
TAG Construction Ltd. $4,620,083.00  
GCL Contracting & Engineering Inc. $4,666,768.00  
Lafarge Canada Inc. $5,361.931.00  
McDonald & Ross Const. Ltd. $5,840,971.00