REQUEST FOR QUOTATIONS

SCOPE OF WORK

The Contractor will provide all labour, materials, equipment and plant and other related services to provide internal meter maintenance and hard surface volunteer meter installation.

The general components of the Work include, but not limited to,
• Maintenance or repair of existing meters, or ancillary components, that are not performing as intended;
• Replacement of meters that have been slated for change outs; and
• Supply and installation of new water meter assemblies for hard surface, exterior locations.

The Contractor is to furnish certificates confirming Work conforms to requirements of Authorities having jurisdiction.

The detailed scope of work is as described on the Supplementary General Conditions (Schedule B – Appendix 1), and Supplementary Specifications (Project) (Schedule B- Appendix 3).

The lack of and/or omission of detailed specifications does not minimize the acceptable levels of service and only the best commercial practices are acceptable.

Contractor to comply with all BC Plumbing Code, BC Fire Marshal, BC Workers’ Compensation Board, National Building Code of Canada, BC Boiler Inspector, BC Electrical Inspector, National Fire Protection Association, and any other authorities having local jurisdiction. Failure to abide by these rules and regulations will result in being immediately escorted from the Place of the Work.

ADDENDA

If the Owner determines that an amendment is required to this RFQ, the Owner’s Representative will post a written addendum on the BC Bid Website at www.bcbid.gov.bc.ca (the “BC Bid Website) and on the Owner Website at www.surrey.ca (the “Owner Website”) and upon posting will be deemed to form part of this RFQ. No amendment of any kind to the RFQ is effective unless it is posted in a formal written addendum on the Owner Website. Upon submitting a Quotation, Contractors will be deemed to have received notice of all addenda that are posted on the Owner Website.

All inquiries related to this RFQ should be directed in writing to the contact person named above.