North Surrey Utility Improvements – Phase 5
Status
Awarded
Closing Date
Revised July 22, 2020
Contact
Ryan Icasiano, Project Supervisor
City of Surrey
604.591.4284 / Ryan.Icasiano@surrey.ca
The Owner invites tenders for:
Construction of approximately 210m of 100mm dia, 150m of 150mm dia, 1175m of 200mm dia watermain, 810m of 200mm dia sanitary sewer, and 160m of 300mm dia storm sewer at the following locations:
- On Robin Crescent between 150th Street and Pheasant Drive.
- On Lark Place between Cul-De-Sac and Oriole Drive.
- On Swallow Drive between Partridge Cr and Pheasant Drive.
- On Jay Crescent between Swallow Drive and Canary Drive.
- On Peacock Place between Jay Crescent and Cul-De-Sac.
On Eagle Place between Jay Crescent and Cul-De-Sac.
Contract Documents are available at:
This tender is being issued electronically through the BC Bid website (www.bcbid.gov.bc.ca) where any interested party may download the tender documents directly from the BC Bid website. No registration, tracking or other recording of tender document holders will be performed by the Owner. All addenda, or further information will be published through the BC Bid website. It is the sole responsibility of the tenderer to monitor the BC Bid website regularly to check for updates.
The Contract is based on the MMCD Platinum Edition and the City’s Supplementary MMCD (January 2016 Edition; amended August 17, 2018)
Addendum No. 1 (.pdf)
(See BC Bid Website - www.bcbid.gov.bc.ca)
Issue Date: February 13, 2020
Tenders are scheduled to close:
Tender Closing Time: 2:00 pm (local time)
Tender Closing Date: February 18, 2020
Tenders should be submitted in a sealed package, marked on the outside with “Tenders for Contract No. 4718-018-11 North Surrey Utility Improvements – Phase 5” and must be received at the first floor Main Reception/Information Desk, Surrey City Hall, 13450-104 Avenue, Surrey, B.C. Canada V3T 1V8.
Name of Owner's Representative:
Ryan Icasiano, Project Supervisor
City of Surrey
604.591.4284 / Ryan.Icasiano@surrey.ca
Company |
Amount |
Corrected Amount |
Awarded to: |
Sandpiper Contracting LLP |
$2,313,411.66 |
No Change |
Awarded. |
Pedre Contractors Ltd. |
$2,631,090.00 |
No Change |
|
Complete Utility Contractors Ltd. |
$2,827,602.75 |
No Change |
|
Drake Excavating (2016) Ltd. |
$2,872,685.52 |
No Change |
|
Jack Cewe Construction Ltd. |
$2,893,695.00 |
No Change |
|
Targa Contracting (2013) Ltd. |
$3,134,156.55 |
No Change |
|
Richco Contracting Ltd. |
$3,189,900.00 |
No Change |
|
Tybo Contracting Ltd. |
$5,355,426.30 |
$3,354,464.50 |
|
J. Cote & Son Excavating Ltd. |
$3,458,138.25 |
No Change |
|
Hyland Excavating Ltd. |
$3,682,072.80 |
No Change |
|
B. Cusano Contracting (2007) Inc. |
$4,342,989.00 |
No Change |