Status

Awarded


Atlas-Apex Roofing

Closing Date

would prefer to receive Quotations on or before May 27, 2022


Revised June 8, 2022

Contact

Sunny Kaila
Manager, Procurement Services 
Finance Department
Tel:  (604) 590-7274
Email:  purchasing@surrey.ca

REQUEST FOR QUOTATIONS

SCOPE OF WORK

The Work covered under this project consists of the furnishing of all superintendence, overhead, labour, materials, tools, equipment, insurance, fuel, transportation and all things necessary for and incidental to the satisfactory performance and completion of Partial Roof Replacement, Surrey Arts Centre located at 13750 88th Avenue, Surrey, British Columbia (the “Place of Work”) in strict accordance with the Specifications and accompanying Drawings and subject to all terms and conditions of the Contract.

The general components of the Work include:

The removal and disposal of the existing roof membrane system in three roof areas, and subsequent installation of a new SBS roofing membrane system including all new drains, flashings, access ladders, etc., and including any necessary temporary disconnect and/or displacement of roof top HVAC equipment, to complete the scope of work as identified in the attached specifications.

The detailed scope of Work is as described in the Special Provisions (Schedule B – Appendix 1), Supplementary Specifications (Project) (Schedule B- Appendix 2), and Contract Drawings (listed below) (Schedule B – Appendix 2A).

The lack of and/or omission of detailed specifications does not minimize the acceptable levels of service and only the best commercial practices are acceptable.

Contractor to comply with all BC Plumbing Code, BC Fire Marshal, BC Workers’ Compensation Board, National Building Code of Canada, BC Boiler Inspector, BC Electrical Inspector, National Fire Protection Association, and any other authorities having local jurisdiction. Failure to abide by these rules and regulations will result in being immediately escorted from the work site.

ADDENDA

If the City determines that an amendment is required to this RFQ, the City Representative will issue a written addendum by posting it on the BC Bid website at www.bcbid.gov.bc.ca and the City website at www.surrey.ca (collectively, the “Websites”), and upon posting, any addenda will form a part of this RFQ. It is the responsibility of Contractors to check the Websites for addenda. The only way this RFQ may be added to, or amended in any way, is by a formal written addendum. No other communication, whether written or oral, from any person will affect or modify the terms of this RFQ or may be relied upon by any Contractor. By delivery of a Quotation the Contractor is deemed to have received, accepted and understood the entire RFQ, including any and all addenda.

All inquiries related to this RFQ should be directed in writing to the contact person named above.